UK
uk
2026
The Stonestreet Green Solar (Correction) Order 2026
UK Statutory Instrument
2026 No. 131
Infrastructure Planning
The Stonestreet Green Solar (Correction) Order 2026
Made
5th February 2026
Coming into force
6th February 2026
The Stonestreet Green Solar Order 2025 (“ the Stonestreet Green Order ”), which granted development consent within the meaning of the Planning Act 2008 (“ the Act ”), contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act.
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act) , the Secretary of State received a written request from the applicant for the correction of errors and omissions in the Stonestreet Green Order.
In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed each relevant local planning authority for the area in which the land to which the Stonestreet Green Order relates is situated, that the request has been received.
The Secretary of State, in exercise of the powers conferred by section 119, and paragraphs 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order.
Citation and commencement
1
This Order may be cited as the Stonestreet Green Solar (Correction) Order 2026 and comes into force on 6th February 2026.
Corrections
2
The Stonestreet Green Order is corrected as set out in Table 1 in the Schedule to this Order, where—
a
column 1 sets out where the correction is to be made;
b
column 2 sets out how the correction is to be made; and
c
column 3 sets out the text which is to be substituted, inserted or omitted.
Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning Delivery & Innovation
Department for Energy Security and Net Zero
5th February 2026
SCHEDULE
Corrections
Article 2
Table 1
(1) Where the correction is to be made (2) How the correction is to be made (3) Text to be substituted, inserted or omitted
Preamble For “Planning Act 2008(a)(“ the 2008 Act ”)” substitute “Planning Act 2008(a) (“ the 2008 Act ”)” Article 2(1) (definition of “cycleway”) After “Road Traffic Act 1988(a)” insert “)” Article 2(1) (definition of “National Grid”) For “2366977” substitute “02366977” Article 10(3) For “(notice of certain works)” substitute “(advance notice of certain works)” Article 16(1) After “powers and duties of” insert “traffic” Article 28(1) For “Paragraph 21(1) of article 21” substitute “Paragraph (1) of article 21” Article 30(1)(a) After “1981 Act(a)” omit “)” Paragraph 33, Part 4, Schedule 13 After “South Eastern Power Networks plc” insert “(company number 03043097)” Paragraph 62, Part 6, Schedule 13 For “3385525, who” substitute “03385525, whose” Part 1, Schedule 14, row 7 (“outline battery safety management plan”), column (3) (“revision number”) For “1” substitute “2” Part 1, Schedule 14, row 14 (“outline operational surface water drainage strategy”), column (1) (“Document name”) After “outline operational surface water drainage strategy” insert “(excluding appendices A, B, C and D)” Part 1, Schedule 14 (new row) After row 14 (“outline operational surface water drainage strategy (excluding appendices A, B, C and D))”, insert a new row
Column (1) “outline operational surface water drainage strategy, appendices A, B, C and D”
Column (2) “7.14(B)”
Column (3) “3”
Column (4) “January 2025”
Part 2, Schedule 14, row 3 (“Chapter 5: Alternatives and Design Evolution”), column (5) (Examination library reference) For “[AS-101]” substitute “[AS-010]” Part 2, Schedule 14 (new row)
After row 9 (“Chapter 13:
Traffic and Access”) insert a new row
Column (1) “Environmental statement”
Column (2) “Chapter 8: Landscape and Views Figures 8.1 - 8.11.4 Part 1 of 2”
Column (3) “5.3(A)”
Column (4) “March 2025”
Column (5) “[REP4-012]”
Part 2, Schedule 14, row 10 (“Figures 10.1 - 10.8: Water Environment”), column (2) (“Replacement or supplementary part”) For “Figures 10.1 - 10.8: Water Environment” substitute “Chapter 10: Water Environment Figures 10.1 - 10.8” Part 2, Schedule 14, row 20 (“Appendix 10.4: Aldington Flood Risk Storage Area Risk Assessment”), column (5) (“Examination library reference”) For “[REP1-042]” substitute “[REP1-034]” Paragraph 1(1), Schedule 16 For “arbitration rales” substitute “arbitration rules”
EXPLANATORY NOTE
(This note is not part of the Order)
This Order corrects errors identified in the Stonestreet Green Solar Order 2025 ( S.I. 2025/1175 ), a development consent order made under the Planning Act 2008, following a request made under paragraph 1(5)(a) of Schedule 4 to that Act.
