wsi/2020/1516
wsi/2020/1516 — <div xmlns="http://www.w3.org/1999/xhtml"> <span xml:lang="en">The Planning Applications (Temporary Modifications and Disapplication) (No. 3) (Wales) (Coronavirus) Order 2020</span> / <span xml:lang="cy">Gorchymyn Ceisiadau Cynllunio (Addasiadau a Datgymhwyso Dros Dro) (Rhif 3) (Cymru) (Coronafeirws) 2020</span> </div>
Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Analyze this law with AI2020 No. 1516 (W. 324)
Town And Country Planning, Wales
The Planning Applications (Temporary Modifications and Disapplication) (No. 3) (Wales) (Coronavirus) Order 2020
Made
10 December 2020
Laid before Senedd Cymru
14 December 2020
Coming into force
9 January 2021
The Welsh Ministers, in exercise of the powers conferred on them by sections 61Z(8) and (9), 62(11), 62R and 333(4B) of the Town and Country Planning Act 1990 , and in exercise of the powers conferred on the Secretary of State by sections 59, 62(1) and (2), 71(1), (2)(a) and (2A) and 333(7) of that Act now exercisable by them (as applied in the case of section 62(1) with modifications by the Development of National Significance (Application of Enactments) (Wales) Order 2016 ), make the following Order.
Title and commencement
1
1
The title of this Order is the Planning Applications (Temporary Modifications and Disapplication) (No. 3) (Wales) (Coronavirus) Order 2020.
2
This Order comes into force on 9 January 2021.
Pre-application consultation: making information available
2
1
The Town and Country Planning (Development Management Procedure) (Wales) Order 2012 is amended as follows.
2
In article 2G(2)(b), for “8 January 2021” substitute “8 October 2021”.
Developments of national significance: making applications
3
1
The Developments of National Significance (Procedure) (Wales) Order 2016 is amended as follows.
2
In article 12(6A)(b), for “8 January 2021” substitute “8 October 2021”.
Julie James
Minister for Housing and Local Government, one of the Welsh Ministers
10 December 2020
EXPLANATORY NOTE
(This note is not part of the Order)
This Order amends the Town and Country Planning (Development Management Procedure) (Wales) Order 2012 (“the 2012 Order”) and the Developments of National Significance (Procedure) (Wales) Order 2016 (“the 2016 Order”). It amends provisions in those Orders to extend the period during which certain requirements are modified or disapplied.
Article 2 amends article 2G(2)(b) of the 2012 Order to extend the emergency period during which the publicity and notice requirements for pre-application consultation are modified. It also extends the emergency period for the purpose of the time which community councils have to make representations on applications notified to them. The emergency period ends on 8 October 2021.
Article 3 amends article 12(6A)(b) of the 2016 Order to extend the period during which hard copies of applications for developments of national significance are not required. That period ends on 8 October 2021.
The Welsh Ministers’ Code of Practice on the carrying out of Regulatory Impact Assessments was considered in relation to this Order. As a result, a regulatory impact assessment has been prepared as to the likely costs and benefits of complying with this Order. A copy can be obtained from the Welsh Government at Cathays Park, Cardiff, CF10 3NQ and is published on the Welsh Government website at www.gov.wales .