uksi/2023/1126
uksi/2023/1126 — The Countryside and Rights of Way Act 2000 (Substitution of Cut-off Date Relating to Rights of Way) (England) Regulations 2023
Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Analyze this law with AI2023 No. 1126
Countryside, England
The Countryside and Rights of Way Act 2000 (Substitution of Cut-off Date Relating to Rights of Way) (England) Regulations 2023
Made
25th October 2023
Laid before Parliament
26th October 2023
Coming into force
17th November 2023
The Secretary of State makes these Regulations in exercise of the power conferred by section 56(2)(a) of the Countryside and Rights of Way Act 2000 .
Citation, commencement and extent
1
These Regulations—
a
may be cited as the Countryside and Rights of Way Act 2000 (Substitution of Cut-off Date Relating to Rights of Way) (England) Regulations 2023;
b
come into force on 17th November 2023;
c
extend to England and Wales.
Modification of the cut-off date in section 56(1) of the Countryside and Rights of Way Act 2000
2
Section 56(1) of the Countryside and Rights of Way Act 2000 has effect, as respects England, as if for “1st January 2026” there were substituted “1st January 2031” .
Trudy Harrison
Parliamentary Under Secretary of State
Department for Environment, Food and Rural Affairs
25th October 2023
EXPLANATORY NOTE
(This note is not part of the Regulations)
Section 56(1) of the Countryside and Rights of Way Act 2000 (c. 37) (“ the Act ”) specifies the cut-off date of 1st January 2026 for the purposes of sections 53 (extinguishment of unrecorded rights of way) and 55 (bridleway rights over ways shown as bridleways) of the Act.
Section 56(2)(a) of the Act empowers the Secretary of State, as respects England, and the National Assembly for Wales (now the Welsh Parliament), as respects Wales, to substitute by regulations that cut-off date for a later date not later than 1st January 2031 (except as respects an area within section 56(4)).
These Regulations provide for that later cut-off date, as respects England, to be 1st January 2031.
An impact assessment has not been produced for this instrument as no, or no significant, impact on the private, voluntary or public sectors is foreseen.