uksi/2020/547 — The Cleve Hill Solar Park Order 2020
Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Analyze this law with AI2020 No. 547
Infrastructure Planning
The Cleve Hill Solar Park Order 2020
Made
28th May 2020
Coming into force
19th June 2020
An application has been made to the Secretary of State for an Order
under section 37 of the Planning Act 2008 (“ the 2008 Act ”) ;
The application was examined by the Examining Authority, which has
made a report to the Secretary of State under section 74(2) of the 2008
Act;
The Examining Authority, having considered the application together
with the documents that accompanied it, and the representations made and
not withdrawn, has, in accordance with section 74 of the 2008 Act made a
report and recommendation to the Secretary of State;
The Secretary of State has considered the report and recommendation of
the Examining Authority, has taken into account the environmental
information in accordance with regulation 4 of the Infrastructure
Planning (Environmental Impact Assessment) Regulations 2017 and has had regard to the documents and matters
referred to in section 105(2) of the 2008 Act;
The Secretary of State, having decided the application, has determined
to make an Order giving effect to the proposals comprised in the
application on the terms that in the opinion of the Secretary of State
are not materially different from those proposed in the
application.
The Secretary of State is satisfied that open space within the Order
land, when burdened with any new rights authorised for compulsory
acquisition under the terms of this Order, will be no less advantageous
than it was before such acquisition, to the persons whom it is vested,
other persons, if any, entitled to rights of common or other rights, and
the public, and that, accordingly, section 132(3) of the 2008 Act
applies.
The Secretary of State, in exercise of the powers conferred by
sections 114, 120, 122 and 123 of the 2008 Act makes the following
Order—
PART 1
PRELIMINARY
Citation and commencement
1
This Order may be cited as the Cleve Hill Solar Park Order and
comes into force on 19th June 2020
Interpretation
2
1
In this Order—
“ the 1961 Act ” means the Land Compensation Act
1961 ;
“ the 1965 Act ” means the Compulsory Purchase
Act 1965 ;
“ the 1980 Act ” means the Highways Act
1980 ;
“ the 1981 Act ” means the Compulsory Purchase
(Vesting Declarations) Act 1981 ;
“ the 1989 Act ” means the Electricity Act
1989 ;
“ the 1990 Act ” means the Town and Country
Planning Act 1990 ;
“ the 1991 Act ” means the New Roads and Street
Works Act 1991 ;
“ the 2004 Act ” means the Energy Act
2004 ;
“ the 2008 Act ” means the Planning Act
2008 ;
“ the 2009 Act ” means the Marine and Coastal
Access Act 2009 ;
“ authorised development ” means the development
and associated development described in Part 1 of
Schedule 1;
“ the book of reference ” means the book of
reference certified by the Secretary of State as
the book of reference for the purposes of the
Order under article 34 (certification of plans and
documents, etc.);
“ cable circuits ” means an electrical conductor
necessary to transmit electricity between two
points within the authorised development and may
include one or more auxiliary cables for the
purpose of gathering monitoring data;
“ cable systems ” means an electrical conductor
comprising a single 400 kilovolt circuit with
three conducting cores or similar equivalent
design;
“ CCTV ” means a closed circuit television
security system;
“commence”, means, (a) in relation to works
seaward of MHWS, the first carrying out of any
licensed marine activities authorised by the
deemed marine licence, save for pre-construction
monitoring surveys approved under the deemed
marine licence and (b) in respect of any other
works comprised in the authorised development,
save for site preparation works, the first
carrying out of any material operation (as defined
in section 155 of the 2008 Act) forming part of
the authorised development and the words
“ commencement ” and “ commenced ” must be construed
accordingly;
“ construction compound ” means a compound
including central offices, welfare facilities,
accommodation facilities, and storage for
construction of the authorised development;
“ energy storage ” means equipment used for the
storage of electrical energy;
“ environmental statement ” means the document
certified as the environmental statement by the
Secretary of State for the purposes of this Order
under article 34 (certification of plans and
documents, etc.) as supplemented by the documents
set out in Schedule 10;
“ existing access road ” means the existing
access road between the existing substation and
Seasalter Road;
“ existing flood defence ” means the existing
bund and integrated infrastructure located beneath
the path known as the Saxon Shore Way and on the
north and west boundaries of the authorised
development in Work No. 9;
“ existing overhead line ” means an 11kilovolt
overhead line owned and operated by UK Power
Networks plc located to the south west of Cleve
Hill within the Order limits;
“ existing substation ” means the existing
substation at Cleve Hill Faversham ME13 9EF owned
and operated by National Grid Electricity
Transmission plc;
“highway” and “highway authority” have the
same meaning as in the 1980 Act ;
“ inverter ” means electrical equipment fitted
to mounting structures required to convert direct
current power generated by the solar modules to
alternating current;
“ land plan ” means the plan or plans certified
as the land plan or plans by the Secretary of
State for the purposes of this Order under article
34 (certification of plans and documents,
etc.);
“the location, order limits and grid
coordinates plan” means the plan certified as the
location, order limits and grid coordinates plan
by the Secretary of State for the purposes of this
Order under article 34 (certification of plans and
documents, etc.);
“ maintain ” includes inspect, upkeep, repair,
adjust, alter, remove, reconstruct and replace to
the extent assessed in the environmental
statement; and “maintenance” must be construed
accordingly;
“ MHWS ” means the highest level which spring
tides reach on average over a period of
time;
“ MMO ” means the Marine Management
Organisation, Lancaster House. Hampshire Court.
Newcastle upon Tyne, NE4 7YH;
“ mounting structure ” means a frame or rack
made of galvanised steel or other material
designed to support the solar modules and
inverters and mounted in piles driven into the
ground;
“ the Order land ” means the land shown on the
land plans which is within the limits of land to
be acquired or used and described in the book of
reference;
“ the Order limits ” means the limits shown on
the land plans and works plan within which the
authorised development may be carried out and land
acquired or used;
“ outline battery safety management plan ” means
the document certified as the outline battery
safety management plan by the Secretary of State
for the purposes of this Order under article 34
(certification of plans and documents, etc.) and
which sets out the battery safety management
principles to be included in the battery safety
management plan pursuant to Requirement 3 of
Schedule 1, Part 2;
“outline construction environmental management
plan” means the document certified as the outline
construction environmental management plan by the
Secretary of State for the purposes of this Order
under article 34 (certification of plans and
documents, etc.);
“outline decommissioning and restoration plan”
means the document certified as the outline
decommissioning and restoration plan by the
Secretary of State for the purposes of this Order
under article 34 (certification of plans and
documents, etc.);
“ outline design principles ” means the document
certified as the outline design principles by the
Secretary of State for the purposes of this Order
under article 34 (certification of plans and
documents, etc.);
“ outline ecological management plan ” means the
document certified as the outline ecological
management plan by the Secretary of State for the
purposes of this Order under article
34 (certification of
plans and documents, etc.);
“outline landscape and biodiversity management
plan” means the document certified as the outline
landscape and biodiversity management plan by the
Secretary of State for the purposes of this Order
under article (certification of plans and
documents, etc.);
“outline skills, supply chain and employment
plan” means the document certified as the outline
skills, supply chain and employment plan by the
Secretary of State for the purposes of this Order
under article 34 (certification of plans and
documents, etc.);
“outline special protection area construction
noise management plan” means the document
certified as the outline special protection area
construction noise management plan by the
Secretary of State for the purposes of this Order
under article 34 (certification of plans and
documents, etc.);
“outline written scheme of investigation”
means the document certified as the outline
written scheme of investigation by the Secretary
of State for the purposes of this Order under
article 34 (certification of plans and documents,
etc.);
“ permissive paths ” means new access tracks
providing restricted public access within the
Order limits along the route shown on the rights
of way plan;
“ relevant planning authority ” means the
planning authority for the area to which the
provision relates;
“ requirements ” means those matters set out in
Part 2 of Schedule 1 (requirements) to this
Order;
“ rights of way plan ” means the plan certified
as the rights of way plan by the Secretary of
State for the purposes of this Order under article
34 (certification of plans and documents,
etc.);
“ site preparation works ” means operations
consisting of pre-construction surveys and/or
monitoring, site clearance, demolition work,
archaeological investigations, environmental
surveys, investigations for the purpose of
assessing ground conditions, remedial work in
respect of any contamination or other adverse
ground conditions, diversion and laying of
services, erection of any temporary means of
enclosure, the temporary display of site notices
or advertisements;
“ solar module ” means a solar photovoltaic
panel designed to convert solar irradiance to
electrical energy fitted to mounting
structures;
“ street ” means a street within the meaning of
section 48 of the 1991 Act, together with land on
the verge of a street or between two carriageways,
and includes part of a street;
“ streets and access plan ” means the plan
certified as the streets and access plan by the
Secretary of State for the purposes of this Order
under article 34 (certification of plans and
documents, etc.);
“ street authority ”, in relation to a street,
has the same meaning as in Part 3 of the 1991
Act ;
“ substation ” means a compound, containing
electrical equipment required to switch,
transform, convert electricity and provide
reactive power compensation, with welfare
facilities, external landscaping and means of
access;
“ transformer ” means a structure containing
electrical switch gear serving to transform
electricity generated by the solar modules to a
higher voltage;
“ undertaker ” means Cleve Hill Solar Park
Limited (company number 08904850);
“ watercourse ” has the meaning given in the
Land Drainage Act 1991 ;
and
“ works plan ” means the plan certified as the
works plan by the Secretary of State for the
purposes of the Order under article 34
(certification of plans and documents,
etc.).
2
References in this Order to rights over land include
references to rights to do or restrain or to place and
maintain, anything in, on or under land or in the air-space
above its surface and references in this Order to the
imposition of restrictive covenants are references to the
creation of rights over the land which interfere with the
interests or rights of another and are for the benefit of
land which is acquired under this Order or which is an
interest otherwise comprised in the Order land .
3
All distances, directions, capacities and lengths referred
to in this Order are approximate and distances between
points on a work comprised in the authorised development are
to be taken to be measured along that work.
4
Any reference in this Order to a work identified by the
number of the work is to be construed as a reference to the
work of that number authorised by this Order.
5
Unless otherwise stated, references in this Order to
points identified by letters are to be construed as
references to the points so lettered on the works
plan.
6
The expression “ includes ” is to be construed without
limitation unless the contrary intention appears.
PART 2
PRINCIPAL POWERS
Development consent etc. granted by this Order
3
1
Subject to the provisions of this Order and the
requirements the undertaker is granted development consent
for the authorised development to be carried out within the
Order limits.
2
Each numbered work must be situated within the
corresponding numbered area shown on the works plan.
Power to maintain authorised development
4
1
The undertaker may at any time maintain the authorised
development, except to the extent that this Order or an
agreement made under this Order provides otherwise.
2
The power to maintain conferred under paragraph
(1) does not
relieve the undertaker of any requirement to obtain any
further licence under Part 4 (marine licensing) of the 2009
Act for offshore works not covered by the deemed marine
licence.
3
This article only authorises the carrying out of
maintenance works within the Order limits.
Consent to transfer benefit of Order
5
1
Except as otherwise provided in this Order, the provisions
of this Order have effect solely for the benefit of the
undertaker.
2
Subject to paragraph (4), the undertaker may with the
written consent of the Secretary of State—
a
transfer to another person (“ the transferee ”) any
or all of the benefit of the provisions of this
Order (including the deemed marine licence, in whole
or in part) and such related statutory rights as may
be agreed between the undertaker and the transferee;
and
b
grant to another person (“ the lessee ”) for a
period agreed between the undertaker and the lessee
any or all of the benefit of the provisions of this
Order (including the deemed marine licences, in
whole or in part) and such related statutory rights
as may be so agreed,
except where paragraph (7) applies, in which case no
consent of the Secretary of State is required.
3
Where an agreement has been made in accordance with
paragraph (2) references in this Order to the undertaker,
except in paragraphs (6) and (8), are to include references
to the transferee or lessee.
4
The undertaker must consult the Secretary of State before
making an application for consent under this article by
giving notice in writing of the proposed application.
5
The Secretary of State must consult the MMO before giving
consent to the transfer or grant to another person of the
whole or part of the benefit of the provisions of the deemed
marine licence.
6
Where the undertaker has transferred any benefit, or for
the duration of any period during which the undertaker has
granted any benefit, under paragraph (2)—
a
the benefit transferred or granted (“the
transferred benefit”) must include any rights that
are conferred, and any obligations that are imposed,
by virtue of the provisions to which the benefit
relates;
b
the transferred benefit will reside exclusively
with the transferee or, as the case may be, the
lessee and the transferred benefit will not be
enforceable against the undertaker; and
c
the exercise by a person of any benefits or rights
conferred in accordance with any transfer or grant
under paragraph (2) is subject to the same
restrictions, liabilities and obligations as would
apply under this Order if those benefits or rights
were exercised by the undertaker.
7
This paragraph applies to any provisions of this Order and
its related statutory rights where—
a
the transferee or lessee is the holder of a
licence under section 6 (licences authorising supply
etc) of the 1989 Act; or
b
the time limits for claims for compensation in
respect of the acquisition of land or effects upon
land under this Order have elapsed and—
i
no such claims have been made;
ii
any such claim has been made and has been
compromised or withdrawn;
iii
compensation has been paid in final
settlement of any such claim;
iv
payment of compensation into court has taken
place in lieu of settlement of any such claim;
or
v
it has been determined by a tribunal or
court of competent jurisdiction in respect of any
such claim that no compensation will be
payable.
8
Prior to any transfer or grant under this article taking
effect the undertaker must give notice in writing to the
Secretary of State and National Grid Electricity
Transmission PLC, and if such transfer or grant relates to
the exercise of powers in their area, to the MMO and the
relevant planning authority.
9
The notice required under paragraphs and (8) must—
a
state—
i
the name and contact details of the person
to whom the benefit of the provisions will be
transferred or granted;
ii
subject to paragraph (10), the date on which
the transfer will take effect;
iii
the provisions to be transferred or
granted;
iv
the restrictions, liabilities and
obligations that, in accordance with paragraph
(6)(c), will apply to the person exercising the
powers transferred or granted; and
v
where paragraph (7) does not apply,
confirmation of the availability and adequacy of
funds for compensation associated with the
compulsory acquisition of the Order land;
and
b
be accompanied by—
i
where relevant, a plan showing the works or
areas to which the transfer or grant relates;
and
ii
a copy of the document effecting the
transfer or grant signed by the undertaker and the
person to whom the benefit of the powers will be
transferred or granted.
10
The date specified under paragraph (9)(a)(ii) in respect
of a notice served in respect of paragraph (8) must not be
earlier than the expiry of five days from the date of the
receipt of the notice.
11
The notice given under paragraph (8) must be signed by the
undertaker and the person to whom the benefit of the powers
will be transferred or granted as specified in that
notice.
12
Sections 72(7) and (8) (variation, suspension, reservation
and transfer) of the 2009 Act do not apply to a transfer or
grant of the whole or part of the benefit of the provisions
of the deemed marine licences to another person by the
undertaker pursuant to an agreement under paragraph (2) .
13
The provisions of articles 8 (street works), 10 (temporary
stopping up of streets), 16 (compulsory acquisition of
land), 18 (compulsory acquisition of rights), 24 (temporary
use of land for carrying out the authorised development) and
(temporary
use of land for maintaining the authorised development) are
to have effect only for the benefit of the named undertaker
and a person who is a transferee or lessee who is
also—
a
in respect of Work Nos. 1 to 9 a person who holds
a licence under the 1989 Act; or
b
in respect of functions under Article 8 (street works) relating to street, a street
authority.
Application and modification of legislative provisions
6
The provisions of the Neighbourhood Planning Act 2017 insofar as they relate to temporary possession of
land under articles 24 (temporary use of land for carrying out the
authorised development) and 25 (temporary use of land for
maintaining the authorised development) of this Order do not apply
in relation to the construction of any work or the carrying out of
any operation required for the purpose of, or in connection with,
the construction, operation or maintenance of any part of the
authorised development.
Defence to proceedings in respect of statutory nuisance
7
1
Where proceedings are brought under section 82(1) (summary
proceedings by a person aggrieved by statutory nuisance) of
the Environmental Protection Act 1990 in relation to a nuisance falling within
paragraph (g) of section 79(1) (noise emitted from premises
so as to be prejudicial to health or a nuisance) of that Act
no order may be made, and no fine may be imposed, under
section 82(2) of that Act if—
a
the defendant shows that the nuisance—
i
relates to premises used by the undertaker
for the purposes of or in connection with the
construction or maintenance of the authorised
development and that the nuisance is attributable
to the carrying out of the authorised development
in accordance with a notice served under section
60 (control of noise on construction site), or a
consent given under section 61 (prior consent for
work on construction site) or 65 (noise exceeding
registered level), of the Control of Pollution Act
1974 ; or
ii
is a consequence of the construction or
maintenance of the authorised development and that
it cannot reasonably be avoided; or
b
the defendant shows that the nuisance is a consequence of the use of the authorised
development and that it cannot reasonably be
avoided.
2
Section 61(9) (consent for work on construction site to
include statement that it does not of itself constitute a
defence to proceedings under section 82 of the Environmental
Protection Act 1990) of the Control of Pollution Act 1974
and section 65(8) of that Act (corresponding provision in
relation to consent for registered noise level to be
exceed), do not apply where the consent relates to the use
of premises by the undertaker for purposes of, or, in
connection with, the construction or maintenance of the
authorised development.
PART 3
STREETS
Street works
8
1
The undertaker may, for the purposes of the authorised
development, enter on so much of any of the streets
specified in Schedule 2 (Streets subject to street works) as
is within the Order limits and may—
a
break up or open the street, or any sewer, drain
or tunnel under it;
b
drill, tunnel or bore under the street;
c
place and keep apparatus under the street;
d
maintain apparatus in the street, change its
position or remove it;
e
repair, replace or otherwise alter the surface or
structure of it; and
f
execute any works required for or incidental to
any works referred to in sub-paragraphs
to
.
2
The authority given by paragraph (1) is a statutory right for
the purposes of sections 48(3) (streets, street works and
undertakers) and 51(1) (prohibition of unauthorised street
works) of the 1991 Act.
3
In this article “ apparatus ” has the same meaning as in
Part 3 of the 1991 Act.
Application of the 1991 Act
9
1
The provisions of the 1991 Act mentioned in paragraph
that apply
in relation to the carrying out of street works under that
Act and any regulations made or code of practice issued or
approved under those provisions apply (with all necessary
modifications) in relation to—
a
the carrying out of works under article 0 (street
works); and
b
the temporary stopping up, temporary alteration or
temporary diversion of a street by the undertaker
under article 11 (temporary stopping up of
streets),
whether or not the carrying out of the works or the
stopping up, alteration or diversion constitutes street
works within the meaning of that Act.
2
The provisions of the 1991 Act
are—
a
subject to paragraph , section 55 (notice of
starting date of works);
b
section 57 (notice of emergency works);
c
section 60 (general duty of undertakers to
co-operate);
d
section 68 (facilities to be afforded to street
authority);
e
section 69 (works likely to affect other apparatus
in the street);
f
section 76 (liability for cost of temporary
traffic regulation);
g
section 77 (liability for cost of use of
alternative route); and
h
all provisions of that Act that apply for the
purposes of the provisions referred to in
sub-paragraphs to .
3
Section 55 of the 1991 Act as applied by paragraph
has effect
as if references in section 57 of that Act to emergency
works included a reference to a stopping up, alteration or
diversion (as the case may be) required in a case of
emergency.
Temporary stopping up of streets
10
1
The undertaker, during and for the purposes of carrying
out the authorised development, may temporarily stop up,
alter or divert any street and may for any reasonable
time—
a
divert the traffic or a class of traffic from the
street; and
b
subject to paragraph , prevent all persons from
passing along the street.
2
Without limiting paragraph (1), the undertaker may use any street
temporarily stopped up under the powers conferred by this
article within the Order limits as a temporary working
site.
3
The undertaker must provide reasonable access for
pedestrians going to or from premises abutting a street
affected by the temporary stopping up, alteration or
diversion of a street under this article if there would
otherwise be no such access.
4
Without limiting paragraph (1), the undertaker may temporarily stop
up, alter or divert the streets set out in column (2) of
Schedule 3 (streets to be temporarily stopped up) to the
extent specified, by reference to the letters and numbers
shown on the streets and access plan, in column (3) of that
Schedule.
5
The undertaker must not temporarily stop up, alter, divert
or use as a temporary working site—
a
any street referred to in paragraph without first
consulting the street authority; and
b
any other street without the consent of the street
authority, which may attach reasonable conditions to
the consent.
6
Any person who suffers loss by the suspension of any
private right of way under this article is entitled to
compensation to be determined, in case of dispute, under
Part 1 (determination of questions of disputed compensation)
of the 1961 Act.
7
If a street authority fails to notify the undertaker of
its decision within 28 days of receiving an application for
consent under paragraph that street authority is deemed
to have granted consent.
Temporary stopping up of public rights of way
11
The undertaker may, in connection with the carrying out of the
authorised development, temporarily stop up each of the public
rights of way specified in column (2) of Schedule 4 (public rights
of way to be temporarily stopped up) to the extent specified in
column (3), by reference to the letters shown on the rights of way
plan.
Agreements with street authorities
12
1
A street authority and the undertaker may enter into
agreements with respect to—
a
any temporary stopping up, alteration or diversion
of a street authorised by this Order; or
b
the carrying out in the street of any of the works
referred to in article 8(1) (street works).
2
Such agreement may, without prejudice to the generality of
paragraph (1)—
a
make provision for the street authority to carry
out any function under this Order which relates to
the street in question;
b
include an agreement between the undertaker and
street authority specifying a reasonable time for
the completion of the works; and
c
contain such terms as to payment and otherwise as
the parties consider appropriate.
PART 4
SUPPLEMENTAL POWERS
Discharge of water
13
1
The undertaker may use any watercourse or any public sewer
or drain for the drainage of water in connection with the
carrying out or maintenance of the authorised development
and for that purpose may lay down, take up and alter pipes
and may, on any land within the Order limits, make openings
into, and connections with, the watercourse, public sewer or
drain subject to the obtaining of consent and approval
respectively pursuant to paragraphs and below.
2
Any dispute arising from the making of connections to or
the use of a public sewer or drain by the undertaker
pursuant to paragraph (1) is determined as if it were a
dispute under section 106 (right to communicate with public
sewers)of the Water Industry Act 1991 (right to communicate with public
sewers).
3
The undertaker must not discharge any water into any
watercourse, public sewer or drain except with the consent
of the person to whom it belongs; and such consent may be
given subject to such terms and conditions as that person
may reasonably impose, but must not be unreasonably
withheld.
4
The undertaker must not carry out any works to or make any
opening into any public sewer or drain pursuant to article
13(1) except—
a
in accordance with plans approved by the person to
whom the sewer or drain belongs, but such approval
must not be unreasonably withheld; and
b
where that person has been given the opportunity
to supervise the making of the opening.
5
The undertaker must not, in carrying out or maintaining
works pursuant to this article damage or interfere with the
bed or banks of any watercourse forming part of a main
river.
6
The undertaker must take such steps as are reasonably
practicable to secure that any water discharged into a
watercourse or public sewer or drain pursuant to this
article is as free as may be practicable from gravel, soil
or other solid substance, oil or matter in
suspension.
7
This article does not authorise the entry into controlled
waters of any matter whose entry or discharge into
controlled waters is prohibited by regulation 12
(requirement for environmental permit) of the Environmental
Permitting (England and Wales) Regulations 2016 .
8
In this article—
a
“ public sewer or drain ” means a sewer or drain
which belongs to a sewerage undertaker, the
Environment Agency, an internal drainage board or a
local authority; and
b
other expressions, excluding watercourse, used
both in this article and in the Environmental
Permitting (England and Wales) Regulations 2016 have
the same meaning as in those Regulations.
9
If a person who receives an application for consent or
approval fails to notify the undertaker of a decision within
28 days of receiving an application for consent under
paragraph or
approval under paragraph that person is deemed to have
granted consent or given approval, as the case may
be.
Protective work to buildings
14
1
Subject to the following provisions of this article, the
undertaker may at its own expense carry out such protective
works to any building located within the Order limits as the
undertaker considers necessary or expedient.
2
Protective works may be carried out—
a
at any time before or during the construction of
any part of the authorised development in the
vicinity of the building; or
b
after the completion of that part of the
authorised development in the vicinity of the
building at any time up to the end of the period of
five years beginning with the day on which that part
of the authorised development is first opened for
use.
3
For the purpose of determining how the powers under this
article are to be exercised, the undertaker may enter and
survey any building falling within paragraph (1) and any land within its
curtilage.
4
For the purpose of carrying out protective works under
this article to a building, the undertaker may (subject to
paragraphs and
)—
a
enter the building and any land within its
curtilage; and
b
where the works cannot be carried out reasonably
conveniently without entering land that is adjacent
to the building but outside its curtilage, enter the
adjacent land (but not any building erected on it)
within the Order limits.
5
Before exercising—
a
a power under paragraph (1) to carry out protective works
to a building;
b
a power under paragraph to enter a building and land
within its curtilage;
c
a power under paragraph to enter a building and
land within its curtilage; or
d
a power under paragraph to enter land,
the undertaker must, except in the case of emergency,
serve on the owners and occupiers of the building or land
not less than 14 days' notice of its intention to exercise
the power and, in a case falling within sub-paragraph
,
,
specifying the protective works proposed to be carried
out.
6
Where a notice is served under paragraph , or , the owner or occupier
of the building or land concerned may, by serving a
counter-notice within the period of 10 days beginning with
the day on which the notice was served, require the question
of whether it is necessary or expedient to carry out the
protective works or to enter the building or land to be
referred to arbitration under article 35
(arbitration).
7
The undertaker must compensate the owners and occupiers of
any building or land in relation to which powers under this
article have been exercised for any loss or damage arising
to them by reason of the exercise of the powers.
8
Where—
a
protective works are carried out under this
article to a building; and
b
within the period of five years beginning with the
day on which the part of the authorised development
carried out in the vicinity of the building is first
opened for use it appears that the protective works
are inadequate to protect the building against
damage caused by the construction, operation or
maintenance of that part of the authorised
development,
the undertaker must compensate the owners and occupiers of
the building for any loss or damage sustained by
them.
9
Nothing in this article relieves the undertaker from any
liability to pay compensation under section 152
(compensation in case where no right to claim in nuisance)
of the 2008 Act.
10
Any compensation payable under paragraph or must be determined, in
case of dispute, under Part 1 (determination of questions of
disputed compensation) of the 1961 Act.
11
In this article “ protective works ”, in relation to a
building, means—
a
underpinning, strengthening and any other works
the purpose of which is to prevent damage that may
be caused to the building by the construction,
operation, maintenance or use of the authorised
development; and
b
any works the purpose of which is to remedy any
damage that has been caused to the building by the
construction, operation, maintenance or use of the
authorised development.
Authority to survey and investigate the land
15
1
The undertaker may for the purposes of this Order enter on
any land shown within the Order limits or which may be
affected by the authorised development and—
a
survey or investigate the land;
b
without prejudice to the generality of
sub-paragraph , make trial holes in such
positions on the land as the undertaker thinks fit
to investigate the nature of the surface layer and
subsoil and remove soil samples;
c
without prejudice to the generality of
sub-paragraph , carry out ecological or
archaeological investigations on such land;
and
d
place on, leave on and remove from the land
apparatus for use in connection with the survey and
investigation of land and making of trial
holes.
2
No land may be entered or equipment placed or left on or
removed from the land under paragraph (1) unless at least 14 days'
notice has been served on every owner and occupier of the
land.
3
Any person entering land under this article on behalf of
the undertaker—
a
must, if so required on entering the land, produce
written evidence of their authority to do so;
and
b
may take with them such vehicles and equipment as
are necessary to carry out the survey or
investigation or to make the trial holes.
4
No trial holes may be made under this article—
a
in land held by or in right of the Crown without
the consent of the Crown;
b
in land located within the highway boundary
without the consent of the highway authority;
or
c
in a private street without the consent of the
street authority,
but such consent must not be unreasonably withheld.
5
The undertaker must compensate the owners and occupiers of
the land for any loss or damage arising by reason of the
exercise of the authority conferred by this article, such
compensation to be determined, in case of dispute, under
Part 1 (determination of questions of disputed compensation)
of the 1961 Act.
6
If either a highway authority or a street authority which
receives an application for consent fails to notify the
undertaker of its decision within 28 days of receiving the
application for consent—
a
under paragraph in the case of a highway
authority; or
b
under paragraph in the case of a street
authority,
that authority is deemed to have granted consent.
7
Section 13 (refusal to give possession to acquiring
authority) of the 1965 Act applies to the entry onto, or
possession of land under this article to the same extent as
it applies to the compulsory acquisition of land under this
Order by virtue of section 125 (application of compulsory
acquisition provisions) of the 2008 Act.
PART 5
POWERS OF ACQUISITION
Compulsory acquisition of land
16
1
The undertaker may acquire compulsorily so much of the
Order land as is required for the authorised development or
to facilitate, or is incidental, to it.
2
This article is subject to paragraph of article
18 (compulsory acquisition of rights) and article 24
(temporary use of land for carrying out the authorised
development).
Time limit for exercise of authority to acquire land compulsorily
17
1
After the end of the period of 5 years beginning on the
day on which this Order is made—
a
no notice to treat is to be served under Part 1
(compulsory purchase under Acquisition of Land Act
1946) of the 1965 Act; and
b
no declaration is to be executed under section 4
(execution of declaration) of the 1981 Act as
applied by article 20 (application of the 1981
Act).
2
The authority conferred by article 24 (temporary use of
land for carrying out the authorised development) ceases at
the end of the period referred to in paragraph (1), except that nothing in
this paragraph prevents the undertaker remaining in
possession of land after the end of that period, if the land
was entered and possession was taken before the end of that
period.
Compulsory acquisition of rights
18
1
Subject to paragraph , the undertaker may
acquire compulsorily such rights or impose restrictive
covenants over the Order land as may be required for any
purpose for which that land may be acquired under article 16
(compulsory acquisition of land), by creating them as well
as by acquiring rights already in existence.
2
Subject to the provisions of this paragraph, article 19
(private rights) and article 26 (statutory undertakers), in
the case of the Order land specified in column (1) of
Schedule 5 (land in which only new rights etc. may be
acquired) the undertaker's powers of compulsory acquisition
are limited to the acquisition of such new rights and the
imposition of restrictive covenants for the purpose
specified in relation to that land in column (2) of that
Schedule.
3
Subject to section 8 (other provisions as to divided land)
and Schedule 2A (counter-notice requiring purchase of land)
of the 1965 Act (as substituted by paragraph of Schedule 6
(modification of compensation and compulsory purchase
enactments for the creation of new rights and imposition of
new restrictive covenants), where the undertaker creates or
acquires an existing right over land or the benefit of a
restrictive covenant under paragraph (1) or (2), the
undertaker is not required to acquire a greater interest in
that land.
4
Schedule 6 (modification of compensation and compulsory
purchase enactments for creation of new rights and
imposition of new restrictive covenants) has effect for the
purpose of modifying the enactments relating to compensation
and the provisions of the 1965 Act in their application in
relation to the compulsory acquisition under this article of
a right over land by the creation of a new right or the
imposition of restrictive covenants.
5
In any case where the acquisition of new rights or
imposition of a restriction under paragraph (1) or is required
for the purpose of diverting, replacing or protecting
apparatus of a statutory undertaker, the undertaker may,
with the consent of the Secretary of State, transfer the
power to acquire such rights to the statutory undertaker in
question.
6
The exercise by a statutory undertaker of any power in
accordance with a transfer under paragraph is subject to the same
restrictions, liabilities and obligations as would apply
under this Order if that power were exercised by the
undertaker.
Private rights
19
1
Subject to the provisions of this article, all private
rights or restrictive covenants over land subject to
compulsory acquisition under article 16 (compulsory
acquisition of land) cease to have effect in so far as their
continuance would be inconsistent with the exercise of the
powers under article 16 (compulsory acquisition of
land)—
a
as from the date of acquisition of the land by the
undertaker, whether compulsorily or by agreement;
or
b
on the date of entry on the land by the undertaker
under section 11(1) (power of entry) of the 1965
Act,
whichever is the earliest.
2
Subject to the provisions of this article, all private
rights or restrictive covenants over land subject to the
compulsory acquisition of rights or the imposition of
restrictive covenants under article 18 (compulsory
acquisition of rights) cease to have effect in so far as
their continuance would be inconsistent with the exercise of
the right or compliance with the restrictive
covenant—
a
as from the date of the acquisition of the right
or the imposition of the restrictive covenant by the
undertaker (whether the right is acquired
compulsorily, by agreement or through the grant of
lease of the land by agreement); or
b
on the date of entry on the land by the undertaker
under section 11(1) of the 1965 Act (power of entry)
in pursuance of the right,
whichever is the earliest.
3
Subject to the provisions of this article, all private
rights or restrictive covenants over land of which the
undertaker takes temporary possession under this Order are
suspended and unenforceable, in so far as their continuance
would be inconsistent with the purpose for which temporary
possession is taken, for as long as the undertaker remains
in lawful possession of the land.
4
Any person who suffers loss by the extinguishment or
suspension of any private right or restrictive covenant
under this article is entitled to compensation in accordance
with the terms of section 152 of the 2008 Act to be
determined, in case of dispute, under Part 1 of the 1961
Act.
5
This article does not apply in relation to any right to
which section 138 (extinguishment of rights, and removal of
apparatus, of statutory undertakers etc.) of the 2008 Act or
article 26 (statutory undertakers) applies.
6
Paragraphs (1)
to have effect
subject to—
a
any notice given by the undertaker before—
i
the completion of the acquisition of the
land or the acquisition of rights or the
imposition of restrictive covenants over or
affecting the land;
ii
the undertaker's appropriation of the
land;
iii
the undertaker's entry onto the land;
or
iv
the undertaker's taking temporary possession
of the land,
that any or all of those paragraphs do not apply
to any right specified in the notice; or
b
any agreement made at any time between the
undertaker and the person in or to whom the right in
question is vested or belongs.
7
If an agreement referred to in paragraph —
a
is made with a person in or to whom the right is
vested or belongs; and
b
is expressed to have effect also for the benefit
of those deriving title from or under that
person,
the agreement is effective in respect of the persons so
deriving title, whether the title was derived before or
after the making of the agreement.
8
Reference in this article to private rights over land
includes reference to any trusts or incidents to which the
land is subject.
Application of the 1981 Act
20
1
The 1981 Act applies as if this Order were a compulsory
purchase order.
2
The 1981 Act, as applied by paragraph (1), has effect with the
following modifications.
3
In section 1 (application of Act), for subsection 2
substitute—
2
This section applies to any Minister, any
local or other public authority or any other body
or person authorised to acquire land by means of a
compulsory purchase order.
.
4
In section 5(2) (earliest date for execution of
declaration) omit the words from “and this subsection” to
the end.
5
Section 5A (time limit for general vesting declaration) is
omitted .
6
In section 5B(1) (extension of time limit during
challenge) for “section 23 (application to High Court in
respect of compulsory purchase order) of the Acquisition of
Land Act 1981, the three year period mentioned in section
5A” substitute “
section 118 (legal challenges relating to
applications for orders granting development consent) of the
2008 Act, the five year period mentioned in article 17 (time
limit for exercise of authority to acquire land
compulsorily) of the Cleve Hill Solar Park Order
2020.
” .
7
In section 6 (notices after execution of declaration), in
subsection (1)(b) for “section 15 of, or paragraph 6 of
Schedule 1 to, the Acquisition of Land Act 1981” substitute “
section 134 (notice of authorisation of compulsory
acquisition) of the Planning Act 2008
” .
8
In section 7 (constructive notice to treat), in subsection
(1)(a), omit the words “(as modified by section 4 of the
Acquisition of Land Act 1981)”.
9
In Schedule A1 (counter-notice requiring purchase of land
not in general vesting declaration), for paragraph 1(2)
substitute—
2
But see article 21(3) (acquisition of subsoil
only) of the Cleve Hill Solar Park Order 2020,
which excludes the acquisition of subsoil only
from this Schedule.
.
10
References to the 1965 Act in the 1981 Act must be
construed as references to the 1965 Act as applied by
section 125 (application of compulsory acquisition
provisions) of the 2008 Act (and as modified by article 22
(modification of Part 1 of the Compulsory Purchase Act 1965)
to the compulsory acquisition of land under this
Order.
Acquisition of subsoil only
21
1
The undertaker may acquire compulsorily so much of, or
such rights in, the subsoil of the land referred to in
paragraph (1) of
article 16 (compulsory acquisition of land) or article 18
(compulsory acquisition of rights) as may be required for
any purpose for which that land may be acquired under that
provision instead of acquiring the whole of the land.
2
Where the undertaker acquires any part of, or rights in,
the subsoil of land under paragraph (1), the undertaker is not
required to acquire an interest in any other part of the
land.
3
The following do not apply in connection with the exercise
of the power under paragraph (1) in relation to subsoil only—
a
Schedule 2A (counter-notice requiring purchase of
land not in notice to treat) to the 1965 Act;
b
Schedule A1 (counter-notice requiring purchase of
land not in general vesting declaration) to the 1981
Act; and
c
Section 153(4A) (blighted land: proposed
acquisition of part interest; material detriment
test) of the 1990 Act.
4
Paragraphs
and are to be
disregarded where the undertaker acquires a cellar, vault,
arch or other construction forming part of a house, building
or manufactory.
Modification of Part 1 of the Compulsory Purchase Act 1965
22
1
Part 1 (compulsory acquisition under Acquisition of Land
Act 1946) of the 1965 Act, as applied to this Order by
section 125 (application of compulsory acquisition
provisions) of the 2008 Act, is modified as follows.
2
In section 4A(1) (extension of time limit during
challenge)— for “section 23 of the Acquisition of Land Act 1981
(application to High Court in respect of compulsory purchase
order), the three year period mentioned in section 4”
substitute “
section 118 of the 2008 Act (legal challenges
relating to applications for orders granting development
consent), the five year period mentioned in article 17 (time
limit for exercise of authority to acquire land
compulsorily) of the Cleve Hill Solar Park Order
2020
” .
3
In section 11A (powers of entry: further notice of
entry)—
a
in subsection (1)(a), after “land” insert “
under
that provision
” ; and
b
in subsection (2), after “land” insert “
under that
provision
” .
4
In section 22(2) (expiry of time limit for exercise of
compulsory purchase power not to affect acquisition of
interests omitted from purchase), for “section 4 of this
Act” substitute “
article 17 (time limit for exercise of
authority to acquire land compulsorily) of the Cleve Hill
Solar Park Order 2020
” .
5
In Schedule 2A (counter-notice requiring purchase of land
not in notice to treat)—
a
for paragraphs 1(2) and 14(2) substitute—
2
But see article 21(3) (acquisition of
subsoil only) of the Cleve Hill Solar Park Order
2020, which excludes the acquisition of subsoil
only from this Schedule
; and
b
after paragraph 29 insert—
PART 4
INTERPRETATION
30
In this Schedule, references to entering on
and taking possession of land do not include doing
so under article 14 (protective works to
buildings), article 24 (temporary use of land for
carrying out the authorised development) or
article 25 (temporary use of land for maintaining
the authorised development) of the Cleve Hill
Solar Park Order 2020.
.
Rights under or over streets
23
1
The undertaker may enter on, appropriate and use so much
of the subsoil of or air-space over any street within the
Order limits as may be required for the purposes of the
authorised development and may use the subsoil or air-space
for those purposes or any other purpose ancillary to the
authorised development.
2
Subject to paragraph , the undertaker may exercise any
power conferred by paragraph (1) in relation to a street without
being required to acquire any part of the street or any
easement or right in the street.
3
Paragraph
does not apply in relation to—
a
any subway or underground building; or
b
any cellar, vault, arch or other construction in,
on or under a street which forms part of a building
fronting onto the street.
4
Subject to paragraph , any person who is an owner or
occupier of land appropriated under paragraph (1) without the undertaker
acquiring any part of that person's interest in the land,
and who suffers loss as a result, is entitled to
compensation to be determined, in case of dispute, under
Part 1 (determination of questions of disputed compensation)
of the 1961 Act.
5
Compensation is not payable under paragraph to any person who is an
undertaker to whom section 85 (sharing cost of necessary
measures) of the 1991 Act applies in respect of measures of
which the allowable costs are to be borne in accordance with
that section.
Temporary use of land for carrying out the authorised development
24
1
The undertaker may, in connection with the carrying out of
the authorised development—
a
enter on and take temporary possession of any of
the Order land in respect of which no notice of
entry has been served under section 11 (powers of
entry) of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been
made under section 4 (execution of declaration) of
the 1981 Act;
b
remove any buildings, agricultural plant and
apparatus, drainage, fences, debris and vegetation
from that land;
c
construct temporary works, haul roads, security
fencing, bridges, structures and buildings on that
land;
d
use the land for the purposes of a temporary
working site with access to the working site in
connection with the authorised development;
e
construct any works, on that land as are mentioned
in Part 1 of Schedule 1 (authorised development);
and
f
carry out mitigation works required pursuant to
the requirements in Schedule 1.
2
Not less than 14 days before entering on and taking
temporary possession of land under this article the
undertaker must serve notice of the intended entry on the
owners and occupiers of the land.
3
The undertaker must not remain in possession of any land
under this article for longer than reasonably necessary and
in any event must not, without the agreement of the owners
of the land, remain in possession of any land under this
article after the end of the period of one year beginning
with the date of completion of the part of the authorised
development for which temporary possession of the land was
taken unless the undertaker has, before the end of that
period, served a notice of entry under section 11 of the
1965 Act or made a declaration under section 4 of the 1981
Act in relation to that land.
4
Unless the undertaker has served notice of entry under
section 11 of the 1965 Act or made a declaration under
section 4 of the 1981 Act or otherwise acquired the land or
rights over land subject to temporary possession, the
undertaker must before giving up possession of land of which
temporary possession has been taken under this article,
remove all works and restore the land to the reasonable
satisfaction of the owners of the land; but the undertaker
is not required to—
a
replace any building, structure, drain or electric
line removed under this article;
b
remove any drainage works installed by the
undertaker under this article;
c
remove any new road surface or other improvements
carried out under this article to any street
specified in Schedule 2 (streets subject to street
works); or
d
restore the land on which any works have been
carried out under paragraph
insofar as the works relate to mitigation works
identified in the environmental statement or
required pursuant to the requirements in Schedule
1.
5
The undertaker must pay compensation to the owners and
occupiers of land which temporary possession is taken under
this article for any loss or damage arising from the
exercise in relation to the land of the provisions of any
power conferred by this article.
6
Any dispute as to a person's entitlement to compensation
under paragraph , or as to the amount of the
compensation, must be determined under Part 1 (determination
of questions of disputed compensation) of the 1961
Act.
7
Nothing in this article affects any liability to pay
compensation under section 152 (compensation in case where
no right to claim in nuisance) of the 2008 Act or under any
other enactment in respect of loss or damage arising from
the carrying out of the authorised development, other than
loss or damage for which compensation is payable under
paragraph .
8
Where the undertaker takes possession of land under this
article, the undertaker is not required to acquire the land
or any interest in it.
9
Section 13 (refusal to give possession to acquiring
authority) of the 1965 Act applies to the temporary use of
land pursuant to this article to the same extent as it
applies to the compulsory acquisition of land under this
Order by virtue of section 125 (application of compulsory
acquisition provisions) of the 2008 Act.
Temporary use of land for maintaining authorised development
25
1
Subject to paragraph , at any time during the maintenance
period (as defined in paragraph (11)) relating to any part
of the authorised development, the undertaker may—
a
enter on and take temporary possession of any land
within the Order land if such possession is
reasonably required for the purpose of maintaining
the authorised development; and
b
construct such temporary works and buildings on
the land as may be reasonably necessary for that
purpose.
2
Paragraph (1)
does not authorise the undertaker to take temporary
possession of—
a
any house or garden belonging to a house;
or
b
any building (other than a house) if it is for the
time being occupied.
3
Not less than 28 days before entering on and taking
temporary possession of land under this article the
undertaker must serve notice of the intended entry on the
owners and occupiers of the land.
4
The undertaker may only remain in possession of land under
this article for so long as may be reasonably necessary to
carry out the maintenance of the part of the authorised
development for which possession of the land was
taken.
5
Before giving up possession of land of which temporary
possession has been taken under this article, the undertaker
must remove all temporary works and restore the land to the
reasonable satisfaction of the owners of the land.
6
The undertaker must pay compensation to the owners and
occupiers of land of which temporary possession is taken
under this article for any loss or damage arising from the
exercise in relation to the land of the provisions of this
article.
7
Any dispute as to a person's entitlement to compensation
under paragraph , or as to the amount of the
compensation, must be determined under Part 1 (determination
of questions of disputed compensation) of the 1961
Act.
8
Nothing in this article affects any liability to pay
compensation under section 152 of the 2008 Act (compensation
in case where no right to claim in nuisance) or under any
other enactment in respect of loss or damage arising from
the maintenance of the authorised development, other than
loss or damage for which compensation is payable under
paragraph .
9
Where the undertaker takes possession of land under this
article, the undertaker is not required to acquire the land
or any interest in it.
10
Section 13 (refusal to give possession to acquiring
authority) of the 1965 Act applies to the temporary use of
land pursuant to this article to the same extent as it
applies to the compulsory acquisition of land under this
Order by virtue of section 125 (application of compulsory
acquisition provisions) of the 2008 Act.
11
In this article “ the maintenance period ” means the period
of 5 years beginning with the date on which a phase of the
authorised development first exports electricity to the
national electricity transmission network.
Statutory undertakers
26
Subject to the provisions of Schedule 7 (protective provisions)
the undertaker may—
a
acquire compulsorily, or acquire new rights or impose
restrictive covenants over, the land belonging to statutory
undertakers shown on the land plan (as certified by the
Secretary of State in accordance with article 34) within the
Order land; and
b
extinguish the rights of, remove, relocate the rights of
or reposition the apparatus belonging to statutory
undertakers over or within the Order land.
Recovery of costs of new connections
27
1
Where any apparatus of a public utility undertaker or of a
public communications provider is removed under article 26
(statutory undertakers) any person who is the owner or
occupier of premises to which a supply was given from that
apparatus is entitled to recover from the undertaker
compensation in respect of expenditure reasonably incurred
by that person, in consequence of the removal, for the
purpose of effecting a connection between the premises and
any other apparatus from which a supply is given.
2
Paragraph (1)
does not apply in the case of the removal of a public sewer
but where such a sewer is removed under article 26
(statutory undertakers), any person who is—
a
the owner or occupier of premises the drains of
which communicated with that sewer; or
b
the owner of a private sewer which communicated
with that sewer,
is entitled to recover from the undertaker compensation in
respect of expenditure reasonably incurred by that person,
in consequence of the removal, for the purpose of making the
drain or sewer belonging to that person communicate with any
other public sewer or with a private sewerage disposal
plant.
3
This article does not have effect in relation to apparatus
to which Part 3 (street works in England and Wales) of the
1991 Act applies.
4
In this article—
“public communications provider” has the same
meaning as in section 151(1) (interpretation of
Chapter 1) of the Communications Act
2003 ; and
“public utility undertaker” has the same
meaning as in the 1980 Act.
PART 6
OPERATIONS
Operation of generating stations
28
1
The undertaker is authorised to use and operate the
generating stations comprised in the authorised
development.
2
This article does not relieve the undertaker of any
requirement to obtain any permit or licence under any other
legislation that may be required from time to time to
authorise the operation of an electricity generating
station.
Deemed marine licence under the 2009 Act
29
The deemed marine licence set out in Schedule
The text continues in the official source.