2017 No. 343
Infrastructure Planning
The Brechfa Forest Wind Farm Connection (Correction) Order 2017
Made
9th March 2017
Coming into force
10th March 2017
The Brechfa Forest Wind Farm Connection Order 2016 (the “Order”) , which granted development consent within the meaning of the Planning Act 2008 (“the Act”) , contains correctable errors within the meaning of the Act.
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, the Secretary of State received, before the end of the relevant period referred to in paragraph 1(6)(a) of that Schedule, a written request from Western Power Distribution (South Wales) Plc to correct errors in the Order. In accordance with paragraph 1(7) of that Schedule, the Secretary of State informed Carmarthenshire County Council that the request had been received.
The Secretary of State, in exercise of the powers conferred by paragraphs 1(4) and (8) of Schedule 4 to the Act, makes the following Order:
Citation and commencement
1
This Order may be cited as the Brechfa Forest Wind Farm Connection (Correction) Order 2017 and comes into force on 10th March 2017.
Corrections
2
The Brechfa Forest Wind Farm Connection Order 2016 is corrected as follows.
1
In Part 3 of Schedule 2 (Plans), substitute the table with the following—
Access and rights of way plans
(1) Drawing title (2) Drawing number (3) Revision
Access and Rights of Way Plans Section A Key Plan – 15/WPD/021 B Access and Rights of Way Plans Section A Plan Series – 15/WPD/022 B Access and Rights of Way Plans Section B Key Plan – 15/WPD/023 A Access and Rights of Way Plans Section B Plan Series – 15/WPD/024 A Access and Rights of Way Plans Section C Key Plan – 15/WPD/025 A Access and Rights of Way Plans Section C Plan Series – 15/WPD/026 A
2
In Part 5 of Schedule 2 (Plans), substitute the table with the following—
Design drawings
(1)Drawing title (2)Drawing number (3)Revision
Key Plan for Design Drawings 15/WPD/100 A 132kV Overhead Line Work No. 1 Profiles 15/WPD/106 B 132kV Overhead Line Work No. 2 Profiles 15/WPD/102 A 132kV Overhead Line Wood Pole Outlines 15/WPD/103 A Design Drawings 132kV Underground Cables 15/WPD/104 A
3
In Part 7 of Schedule 2 (Plans), substitute the table with the following—
Heritage designations plans
(1)Drawing title (2)Drawing number (3)Revision
Key Plan for Heritage Designations (Section A) 15/WPD/033 B Key Plan for Heritage Designations (Section B) 15/WPD/035 A Key Plan for Heritage Designations (Section C) 15/WPD/037 A Heritage Designations Plan (Section A) 15/WPD/034 B Heritage Designations Plan (Section B) 15/WPD/036 A Heritage Designations Plan (Section C) 15/WPD/038 A
4
In Part 8 of Schedule 2 (Plans), substitute the table with the following—
Land plans
(1)Drawing title (2)Drawing number (3)Revision
Land Plans Section A Key Plan – 15/WPD/009 B Land Plans Section A Plan Series – 15/WPD/010 D Land Plans Section B Key Plan – 15/WPD/011 A Land Plans Section B Plan Series – 15/WPD/012 D Land Plans Section C Key Plan – 15/WPD/013 A Land Plans Section C Plan Series – 15/WPD/014 C
5
In Part 9 of Schedule 2 (Plans), substitute the table with the following—
Trees and Hedges with the potential to be affected plans
(1)Drawing title (2)Drawing number (3)Revision
Trees and Hedges with the Potential to be Affected Plans Section A Key Plan – 15/WPD/039 B Trees and Hedges with the Potential to be Affected Plans Section A Plan Series – 15/WPD/110 B Trees and Hedges with the Potential to be Affected Plans Section B Key Plan – 15/WPD/041 A Trees and Hedges with the Potential to be Affected Plans Section B Plan Series – 15/WPD/111 A Trees and Hedges with the Potential to be Affected Plans Section C Key Plan – 15/WPD/043 A Trees and Hedges with the Potential to be Affected Plans Section C Plan Series – 15/WPD/044 A
6
In Part 10 of Schedule 2 (Plans), substitute the table with the following—
Works plans
(1)Drawing title (2)Drawing number (3)Revision
Works Plans Section A Key Plan – 15/WPD/015 B Works Plans Section A Plan Series – 15/WPD/107 D Works Plans Section B Key Plan – 15/WPD/017 A Works Plans Section B Plan Series – 15/WPD/109 B Works Plans Section C Key Plan – 15/WPD/019 A Works Plans Section C Plan Series – 15/WPD/020 B
7
In Requirement 5(4) of Schedule 3 (Requirements), replace “A/WP/PS/7” with “A/WP/PS/1 Sheet 7 of 7”,
Signed by the authority of the Secretary of State for Business, Energy and Industrial Strategy
Giles Scott
Head of Energy Infrastructure Planning and Coal Liabilities
Department for Business, Energy and Industrial Strategy
9th March 2017
EXPLANATORY NOTE
(This note is not part of the Order)
This Order corrects errors in the Brechfa Forest Wind Farm Connection Order 2016, which granted development consent under the Planning Act 2008, following a written request from Western Power Distribution (South Wales) Plc under paragraph 1(5)(a) of Schedule 4 to that Act.